This form is to be used in preparation for the public review. 

Checklist completed by:

Amy Palmer 

Date Completed:

June 7, 2016 

Project Name and Version:

SDTMIG v3.3 Batch 3 

30-DAY PUBLIC REVIEW POSTING PREPARATION AND APPROVALSNotes

  • Team Lead has created the public review package, and submitted it to the CDISC Publication Committee.

  • The CDISC Publication Committee submitted the public review package to the SRC

  • Program Management notified CDISC Communications and Wiki Administrator at least 3 days before planned public review posting.

  • Presentation materials have been developed and sent to the Education Liaison. (if applicable)

  • Public Webinar has been conducted and recorded by the Education Liaison. (if applicable)

  • Project team has reviewed the final Education Materials Package. (if applicable)
N/A
30-DAY PUBLIC COMMENT POSTING PERIOD
  • SRC has approved posting for 30-day public review period.

  • SRC Chairperson has approved public review announcements.

  • SRC approval for public review has been documented and archived on the Portal.

  • CDISC Communications posted announcements (see public review posting instructions).

  • Wiki Administrator released the draft standard for public review on the Wiki.

CLOSING THE 30-DAY PUBLIC COMMENTING PERIOD
  • Project Manager exported comments from JIRA into a consolidated spreadsheet. Contact the Wiki Administrator for assistance.

  • Wiki Administrator archived the draft standard and comments from JIRA.

  • CDISC Communications removed the public review announcement from the CDISC website
 