Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

RoleResponsibilities
Project Manager
  1. Works with the Publication Committee to finalize the comment resolution spreadsheet
, refresh
  1. Refresh the TA Specification
and publish
  1. Publish the document.
Communications Team
  1. Posts the standards on CDISC portal and announces availability.
Education Representative 
  1. Post education course and announces availability.
SCR
  1. Approves final change.




Instructions

Describe each step to be taken to complete the scope of this Work Instruction in the prescribed sequence. Use active verb in the Instructions column.

Step #RoleInstructions
1.0Communications TeamPosts the standards on www.cdisc.org
1.1Communications TeamAnnounces availability of the new standard package.
2.0Education RepresentativePosts education course.
2.1Education RepresentativeAnnounces availability of the education course.
3.0Project ManagerEnsures all project documents are posted on the portal.
4.0Project ManagerSubmits package as final after resolving all provisional dependencies.
5.0SCRApproves the change to final. 
6.0Project TeamCreates a record of issues they have determined will be addressed in future versions of the standard.

General Workflow

Include a general workflow diagram that summarizes this Work Instruction.

...