Step #RoleInstructions
1.0Project Manager

Assembles project team

2.0CDISC Education TeamAssigns an Education Representative to work with the project team.
3.0Education Representative

The Education Representative conducts an initial meeting to orient the Project Manager and team on training development procedures and templates. 

3.1Foundational education sub-team leadsCollaborates with CDISC education team for their respective foundational standards
4.0Project TeamReviews of applicable questionnaires and scales used and initiates the process for collecting the required copyright permissions.
4.1QRS RepresentativeExpands the initial gap analysis, identifies questionnaires that are needed and initiates the process for acquiring permissions. 
4.2QRS Representative / Clinical ExpertReviews the list of instruments and identifies those that need development.
5.0Technical WriterSets up standard space in the wiki.
6.0Metadata DeveloperModels Concepts
6.1Metadata Developer (Concept Developer)Defines any concepts that have not been addressed in current CDISC standards to reach a common understanding with the Clinical Expert.
7.0Clinical ExpertEvaluates new and different research concepts to ensure the data are clearly understood.
8.0Metadata DeveloperCreates concept maps
9.0SDTM Expert / SDS TeamWorks with the Project Team to address areas not covered by the current SDTMIG.
10.0Metadata DeveloperRefines Deliverable Plan. 
11.0Clinical Expert / Clinical SMEsEnsures the core concepts under development are adequate and appropriate, and that there are no significant concepts missing.
12.0Project TeamRefines the concept maps and list of concepts as necessary.
13.0Project Manager

Submits all examples to the Global Governance Group (GGG) for approval. 

13.1Project TeamRefines the examples based on GGG feedback.
14.0GGG (Global Governance Group)Approves the modeling before the team can move to stage 2
15.0Project ManagerUpdates the project plan and project charter, and notifies all parties involved. Performs CDISC project review.