Step #RoleInstructions
1.0Project Manager

Assembles project team

2.0CDISC Education TeamAssigns an Education Representative to work with the project team.
3.0Education Representative

The Education Representative conducts an initial meeting to orient the Project Manager and team on training development procedures and templates. 

3.1Foundational education sub-team leadsCollaborates with CDISC education team for their respective foundational standards
4.0Project TeamReviews of applicable questionnaires and scales used and initiates the process for collecting the required copyright permissions.
54.01QRS RepresentativeExpands the initial gap analysis, identifies questionnaires that are needed and initiates the process for acquiring permissions. 
54.12QRS Representative / Clinical ExpertReviews the list of instruments and identifies those that need development.
65.0Technical WriterSets up standard space in the wiki..




Metadata Developer Defines any concepts that have not been addressed in current CDISC standards to reach a common understanding with the Clinical Expert.

Clinical ExpertProject ManagerEvaluates new and different research concepts with the assistance of the Clinical Expert to ensure the data are clearly understood. Performs check of concepts with targeted CDISC community. Concept maps illustrating relationships among the data are developed to facilitate this process.

Metadata DeveloperCreates concept maps

SDTM Expert / SDS TeamWorks with the Project Team to address areas not covered by the current SDTMIG. It is crucial that the SDTM Expert is included in this process and works closely with the SDS team. Any issues that cannot be resolved for the first version of the standard must be placed on the SDS issues list so that resolution can be addressed in a later version.Project ManagerSubmit concept maps to MRC for Approval




Clinical Expert and other / Clinical SMEsChecks concepts and concept maps. The purpose of the review is to ensure the Ensures the core concepts under development are adequate and appropriate, and that there are no significant concepts missing. This review limited to the team members, SMEs, FDA and other identified stakeholders.

Metadata Developers Forum and Concept Modelers Forum

  • Teams are expected to take any examples about which they have questions to the appropriate forum.
  • Results of discussions at the forum should be recorded in the forum’s Wiki space. Documentation must include rationales for decisions and labels, including label for the project (e.g., which TA).
  • Terminology decisions are currently documented on Terminology pages within the Wiki TA projects and in Terminology team spreadsheets in the portal

Project TeamRefines the concept maps and list of concepts as necessary.

Project Manager

Submits all examples to the Global Governance Group (GGG) for approval. 


Project TeamRefines the examples based on GGG feedback.

GGG (Global Governance Group)Approves the modeling before the team can move to stage 2

Project ManagerUpdates the project plan and project charter, and notifies all parties involvedProject ManagerCalls for a CDISC project review with CDISC Project Management and Experts.

General Workflow

Include a general workflow diagram that summarizes this Work Instruction.

...