Purpose

The purpose of the Public Review is to develop widespread consensus for the proposed standard by allowing for broad comment by the general publicthis stage is to prepare the posting package and announce availability of the new standard.

Scope

The deliverables deliverable for Stage 3b are the standards document posting 3c is the publication package, including electronic metadata as appropriatecomplete metadata in SHARE and Education materials (if applicable).

Prerequisites

...

Standards document posting package, including electronic metadata as appropriate.

Definitions

List terms (abbreviations, acronyms, technical jargon) referenced in this Work Instruction useful at adding clarity. Put "Not applicable." if this section is not applicable.

TermDefinition
SDTMStudy Data Tabulation Model. Provides a standard for organizing and formatting data to streamline processes in collection, management, analysis and reporting. Implementing SDTM supports data aggregation and warehousing; fosters mining and reuse; facilitates sharing; helps perform due diligence and other important data review activities; and improves the regulatory review and approval process. 
CDASH Clinical Data Acquisition Standards HarmonizationEstablishes a standard way to collect data consistently across studies and sponsors so that data collection formats and structures provide clear traceability of submission data into the Study Data Tabulation Model (SDTM).
ADaMAnalysis Data Model.  ADaM defines dataset and metadata standards that support: efficient generation, replication, and review of clinical trial statistical analyses, an traceability among analysis results, analysis data, and data represented in the Study Data Tabulation Model (SDTM).​
SRCSHARE
GGG (Global Governance Group)Responsible for reviewing and approving all draft standards. This group is composed of representatives from each of the foundational teams who have been empowered to review and approve modeling decisions on behalf of their team. The GGG meetings are open to any CDISC team member.
SCR




Roles & Responsibilities

Lists all roles and their responsibilities relevant to this Work Instruction.

RoleResponsibilities
Project Manager
CDISC ITPosts draft standard package for public review (New Term Request Spreadsheet).
Copy Editor

Performs a quality check of draft standards prior to submission to GGG for approval to post for publication.

Works with the Publication Committee to finalize the comment resolution spreadsheet, refresh the TA Specification and publish the document.
Communications TeamPosts the standards on CDISC portal and announces availability.
Education Representative Post education course and announces availability.
SCRApproves final change.GGGReviews and approves all draft standards. Reviews responses to Public Review comments. Reviews and approved any normative content changes. 




Instructions

Describe each step to be taken to complete the scope of this Work Instruction in the prescribed sequence. Use active verb in the Instructions column.

Step #RoleInstructions
1.0Project ManagerCommunications TeamPosts the standards on www.cdisc.orgWorks with the Education Team to schedule a public webinar to coincide with the commencement of the public review period. The purpose of this webinar is to announce the Public Review and help ensure an adequate number of comments are received.
1.1Project ManagerNotifies the Education Team of the planned public review posting dates and verifies that the presentation slides are developed. 
1.2Education TeamRecords the webinar to be used as a resource for developing training material. 
Communications TeamAnnounces availability of the new standard package.
2.0Education RepresentativePosts education course.
2.1Education RepresentativeAnnounces availability of the education course2.0CDISC ITPosts draft standard package for public review (New Term Request Spreadsheet).
3.0Project ManagerResponds to Public Review comments and update the draft document
3.1GGGReviews responses to Public Review comments.
4.0Project ManagerCreates a list of issues for V2.
Ensures all project documents are posted on the portal.
4.5.0Project ManagerSubmits draft standard posting package to publication committee.
5.1GGGReviews and approved any normative content changes. 
5.2Project ManagerSubmits additional terminology requests and complete other required activities as necessary (QRS).5.3Project ManagerSends final document to copy editor for reviewfinal after resolving all provisional dependencies.
5.40Copy Editor

Performs a quality check of draft standards prior to submission to GGG for approval to post for publication

6.0Project ManagerSubmits provisional/final version with resolved comments to SRC.
7.0Project Manager Resolves issues noted by SRC.
SCRApproves the change to final. 8.0SRCReviews and approves package for public release.



General Workflow