Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...


AccountableMilestoneComments

Stage 0 – Scoping & Planning 

0.1Project ManagerCreate project artifacts (Jira, Wiki)For TAUGs, grant proposal has been signed and project is slated to start
0.2Project Manager Create project plan from templateI think this will be a new action for Alana, normal for Dana except that it comes from a template now which can be added to in 0.5
0.3Project ManagerReview scope

For TAUGs, this includes review of signed off Proposal (eg. 18 months, 10 concepts)


0.4Project Manager

Create project charter Wiki page


Wiki page can contain proposal but high level details should be included on the page. 

Charter page should be from a common template so that all project charters could be exported and seen in a spreadsheet.  

Would it be possible to identify common information that both SD and DS are interested in to create template? That way projects that don't include SD would still be consistent and they'd be able to be reported along with the SD, SD/DS projects.

0..5Project ManagerUpdate project planAt this time additional items are added to Jira plan that was created by the template.
0.6Project ManagerScope approval if requiredFunder, project team, head of standards
0.7Project Manager Review project plan, scope, and Wiki structures with Metadata Analyst

PM and Metadata Analysts meet at start of the project to make sure both departments aligned, however, PM and Metadata Analysts should continue to review during Stage 1 & 2 and should plan meeting cadence at this time.

Stage 1 – Development of Biomedical Concepts

1.1

Project Manager 

Standards Developer

Analyze concept list requirements 

Based on concept list, do we need a diagram

Do we need to explain further

If yes, start CMAPS (1 or more)

1.2

Standards Developer

Create concept mapsCMAPS
1.3

Clinical Expert

Review concepts maps Review with clinical and/or relevant SMEs (if applicable)
Stage 2 – Development of Draft Standards 
2.2Standards DeveloperConcept 1

For each concept, create:

Content - Examine concepts and consider what specific content is needed as part of the final standards product.

Examples - Creates sample data to improve understanding of all key concepts.  CDASH, SDTM, ADaM and they'd all flow through (sometimes no ADaM ).  Sometimes just text, list of lab tests


Involve QRS and CT
assume this is a lead rep.





2.3Standards DeveloperConcept 2
2.4Standards DeveloperConcept 3
2.5Standards DeveloperConcept 4
2.6Standards DeveloperConcept 5
2.7Standards DeveloperConcept 6
2.8Standards DeveloperConcept 7
2.9Standards DeveloperConcept 8
2.10Standards DeveloperConcept 9
2.11Standards DeveloperConcept 10
2.12Project ManagerTeam Review before GGG
2.13Project ManagerResolution of team review issues

Project ManagerTA specification creation
2.14Project ManagerFinal review of TAUG with Metadata Analyst

TAUGs are not currently in library, but it would be good to establish this now for when they do get added.  This would actually be a final, since they would have been meeting every month, 3 months, etc. as necessary.

not applicable for now

2.15Project ManagerMaterial prepared for GGG Internal Review (IR)
2.13

Project Manager

Schedule GGG review
2.16GGG LeadGGG meeting for IR approval
Stage 3a - Internal Review
3.a.1Project ManagerInternal ReviewMake necessary updates
3.a.2Project ManagerIR comment resolution
3.a.3Copy EditorPre-public review copy editing

This needs to start during IR and Questions / Comments need to be entered into Jira.

3.a.4Project ManagerPrepare for GGG Public Review (PR)
3.a.5Project ManagerSchedule GGG meeting for PR approval
3.a.6GGG LeadSign-off for PR Approval
Stage 3b - Public Review
3.b.1Software EngineerScrape and load to Stage/Prod as Draft
3.b.2Project ManagerPost for Public Review (Website, Wiki)*done by ticket to Comms
3.b.3Project ManagerPublic Review (PR)Make necessary updates (Erin puts in tickets to make updates)
3.b.4Project ManagerPR comment resolutionthis is PM but blue because it's SD/DS effort
3.b.5Project ManagerFDA review
3.b.6Project ManagerFDA comment resolution
3.b.7Software EngineerScrape and load to QA
3.b.8Project ManagerPerform UAT with Metadata AnalystThis includes identifying reviewers, etc.
3.b.9Project ManagerUAT Comment resolution with Metadata Analyst
3.b.10Project ManagerUAT Validation of fixes
3.b.11Project ManagerPub material ready for GGG
3.b.12Project Manager

GGG meeting for Pub Publication approval


3.b.13Project ManagerGGG sign-off of public review comment resolution rep.s
Stage 3c - Publication
3.c.1Head of StandardsHeads of Standards Approval
3.c.2Copy EditorFinal Copy-editing Check 
3.c.3Project ManagerAddress copy-editing comments 
3.c.4Project ManagerLockdown Wiki space

 

3.c.5Copy editorCreate PDFPublication
3.c.6Project ManagerExport public review comments
3.c.7Software EngineerScrape and load to Stage/Prod 
3.c.8Project ManagerPost on WebsiteRaise a ticket to IT to post on Website
3.c.9Project Manager

Archive Wiki space

Raise a ticket to Comms to Archive

space